The RSR’s TPO spent its last week in the FRT’s shed as Mike (above) and Paul (below) fitted the brush strips alongside the sliding doors and John Dixon cleaned the windows and touched up some of the paintwork. 
It It is planned that the TPO coach will be moved out of the shed today and replaced by the Great Eastern Railway Royal Saloon No. 5 which will need a little TLC to its upholstery and exterior varnish after being in use at Beamish for eight years. And, of course, there are still some jobs that we never finished off in the first place!
Chris Rycroft and Howard Fletcher are seen here between Caliban‘s frames last Wednesday manoeuvring a jack hammer into position in order to try and remove another of the very stubborn spring hanger pins. One pin was removed on Wednesday but it looks as if it will be necessary to drill out the other pins, which will no doubt take some considerable time and effort.
Outside the shed, tarmac was laid on Friday in preparation for the creation of the Ribble Steam Railway’s new children’s playground.
John and Fred were on the mess room roof in order to fix a new outside aerial, and the completed tarmac and aerial can be seen here.
Inside the mess room John has fitted a much needed new towel rail.
Keith has taken delivery of two new sheets of steel as he proceeds with the re-building of the top of the tender frames. With the TPO coach finished, Mike reverted to chasing up electrical faults on the FRT’s former RMB and discovered new fuses that didn’t actually contain any fuse wire..!
Cumbria arrived at Embsay as scheduled last Thursday and was pressed into traffic straight away on Saturday and Sunday. Alan and Tim each went for a footplate ride on the old ‘Red Rocket’ on Saturday and proclaimed that it was good to see it back in action closer to home. Cumbria is seen here at Embsay on Saturday ready to depart with the 13.30 train to Bolton Abbey.
Also seen here at Embsay are the new small boiler tubes for 5643 which had arrived and are now waiting to be fitted by Andy Booth.
Finally there was a very long meeting of, the Trustees last night, which finished at 11.45 pm, having been on the go since 8 pm. It seems that the forthcoming challenges of the new General Data Protection Regulation were of rather more interest to everyone than might have been anticipated! Members should expect a letter on the subject in the post over the next week or so.
The people from PPS Graphics from nearby Anchorage Business Park turned up as scheduled on Wednesday morning and, with Tim’s assistance, applied the fantastic graphics to the bodysides of the TPO.
The TPO coach is seen here after varnishing had been completed.
The paintwork on the RSR’s TPO is almost complete following the working parties on Wednesday and Friday.
The yellow stripes along the lower panels of the body were added as was the orange electrical warning line on the gutter edges.
The painting of the bogies was completed on Friday with Roger adding the final touches of colour before he disappears on holiday. The vinyls should be added on Wednesday followed by a final coat of varnish on Friday.
We are pleased to be able to report that Ade should now be back at home after going under the knife during a four hour operation on Thursday. He tells us that the hospital food was OK but that he couldn’t find the mini-bar! He is still feeling rather sore and reckons that it will be a little while before he will be able to continue his efforts to dismantle Caliban‘s springs.
Finally, in the mess room, Fred brought in an inside aerial to try out on the TV but was unable to get much of a picture with it. It looks as if we will have to invest in a proper outdoor aerial sometime.
The photo shows the coach in Royal Mail red masked up ready to receive the yellow stripes along the lower panels. As can be seen from the shining bogies, Fred, Roger and John Davis have also been hard at work down below. It is planned that the vinyl Travelling Post Office lettering will be applied to the body sides next Wednesday, after which a finishing coat of varnish is scheduled for the Friday. It shouldn’t be too long after that before the coach is transferred into the museum.
Ade and Howard have finally managed to release the first of Caliban‘s spring hangers, where the steel pins are proving to be well and truly seized up. Howard is seen here attempting to remove the second of the spring hangers. Howard is also looking to call in reinforcements as chief dismantler Adrian is due to go under the knife in Preston Royal Infirmary tomorrow so will be on light duties for a while after that. Good luck Ade!
Keith continues to be on the look out for components for Wootton Hall and has been fortunate to obtain a second hand clack valve courtesy of Andy Booth. Please see Keith if you would like to contribute to the purchase of this or the two new snifting valve castings which were mentioned in last week’s blog.
Keith has also been fabricating two plates to cover the cylinders on Wootton Hall, one of which is seen in position here.
As mentioned in last week’s blog, the Ribble Steam Railway’s Spring Steam Gala took place on Saturday and Sunday with four locomotives in operation, including visiting Hudswell Clarke 0-6-0T Gothenburg from the East Lancashire Railway which is seen here departing from Riverside station with the first train on Saturday.
The Gala marked the introduction into service of the FRT’s former RMB buffet car No. 1812, which was placed in the centre of the three coach rake, and very smart it looked. Draught beer has been re-installed to the bar and Brent is seen here drawing off the first drink of the day.

John Dixon is pictured here in the process of applying gloss paint on Saturday and it is planned to put on another gloss coat on Wednesday, so a dust curfew is required in the shed for that day. John Davis, Fred and Roger have been continuing their task of painting the frames and bogies and are nearly at an end with this part of the project. Paul Balshaw has been attending to the missing rubbing plates on one of the corridor connections.
Work has now commenced in earnest on the painting of the RSR’s TPO coach, and John Dixon is seen here painting the corridor ends.
Now that this has been achieved, it is planned to start painting the body sides next Friday.
Down below, John Davis, Paul Newton, Fred and Roger have been continuing their work in painting the frames, headstocks and bogies. 
Paul Balshaw also made a start on cleaning up the interior of the coach now that the filling and sanding has finished.
Ade, Howard and Alan have been stripping the axleboxes on Caliban, although this has been a slow process as it is many years since they have been apart. 
It is planned that he will return again shortly to complete the job.
The work is taking a little longer than anticipated owing to some distortion that occurred during the original welding and the need to adopt a different technique to prevent a recurrence.
A large selection of books, videos and vinyl LPs, seen here stacked in the mess room, will also be available for sale.
Outside our shed, work has started on preparing the ground ready for tarmac to be put down, probably this next week. This is in advance of the new children’s play area which will be created between the FRT shed and the museum.
Alan looked at the weather forecast and decided to delegate the role of owner’s representative for FR 20 at this weekend’s steamings at Locomotion to member Brian Goodfellow, who lives locally to Shildon.
This was a sensible decision as Alan was due to play at a St. Patrick’s Day gig with our folk band Live Steam at Cark on Saturday evening and, in the event, the local mountain rescue teams had to turn out to rescue people from the A66 on Saturday night!
Mike can be seen here offering suitable supervisory advice to John Davis from the comfort of his chair as John paints a bogie.
and an eccentric rod…
Keith is asking for expressions of interest to sponsor these items – the clack valve is £400 and the eccentric rod £375 .
John Dixon is seen here working on the west corridor end before applying some primer to bare metal.
Ade is seen here attending to one of the hornstays.
Back at Preston, John’s beloved Caliban was jacked further up into the stratosphere on Wednesday by Ade and Howard to allow the axleboxes to be examined.
Dismantling them is proving to be a painstaking job as the pins have been exposed to the elements and not been touched for many a year, making the grease they were coated with extremely hard.
However, after the application of some release oil by Alan, Howard pursued the task on Saturday and reckoned that he was starting to see some movement in the pins, but there is some way to go yet!
The north side bogies have now been cleaned up, primed and are now receiving undercoat.
Finally for this week, one of the other tasks that has been undertaken by FRT members is the restoration of a signal post, which has been shot blasted and then painted by David. It is seen here on Saturday being driven by Matt Bedford on its way to the RSR Museum where it was united with a set of signal lights and is now ready to be wired up.
Both Alan and Alison were at Locomotion, Shildon, for the first of FR 20’s steamings in 2018. Perhaps, then, Alan shouldn’t have been surprised to find the campervan festooned with balloons and banners proclaiming the fact that he is now an octogenarian – but still of course driving his beloved steam trains! Needless to say, a suitably inscribed cake appeared at his celebratory dinner that evening.





At Preston, Adrian and Howard spent Wednesday jacking up Caliban‘s frames with the aim of being able to release the wheels.
Work has proceeded with the body overhaul of the RSR’s TPO coach with lots more filling and sanding taking place. Paul Balshaw made his second appearance (yes, it seems that he is keen to continue with us) and worked alongside Mike and John Davis who were cleaning up the corridor ends and the north side bogies.
Roger once again continued his painting mission on the frames.
John Dixon tells us that he has almost finished fitting out the mess room, having made progress with boxing in the water pipes and with the cabinet skirting panels, and should shortly be ready to end his winter hibernation in there.