A few pictures this week of progress in fitting the new injector steam valves on Furness Railway No. 20. The first, taken last Wednesday, shows Alan marking up one of the new flanges that is being fitted to the left hand steam pipe.
The right hand steam pipe can be seen lined up nicely with the valve after a bit of tweaking.
It was left to Sam to remove the pipes and the new valves so that the cladding sheets could be fitted.
Both cladding sheets were duly fitted on Friday by Roger, John Dixon and Tim. The sheets are a ‘nib fit’, so it took some time to get them exactly in the right location and screwed down without damage to the new paintwork.
The next stage will be to silver solder the flange joints and to fit the brasswork around both ends of the cladding sheets. Then it will be possible to fit the cab sides and open up plenty more work including the finishing paintwork on the cab sides and valances.
We are pleased to be able to report that Keith was happy with the lubrication trials on the first two of Wootton Hall‘s tender axleboxes. The chassis is now being raised so that the wheelsets can be rolled into position underneath.
Unfortunately, the holidays mean that there won’t be a blog next week.
This should pave the way for placing the tender chassis on to the wheels in due course.
Tim has produced a dozen new lubrication trimmings which will siphon oil from the upper oil tray. The first two axleboxes have now been assembled and fitted with the new pads and trimmings and the rate of flow of oil from the trimmings will be checked over a period of time.
Last Wednesday saw another welcome step forward in the overhaul of Furness Railway No. 20. With the assistance of the Ribble Rail staff, FR 20 was pulled out of the FRT shed to enable the hi-ab on the self propelled TRAM to lift into place the dome cover and cab spectacle plate. Tim is seen wielding a spanner during the course of tightening up the nuts holding the spectacle plate in position.
Whilst out of the shed, it was also a good opportunity to re-fit the ashpan, which needs to be done whilst the engine is situated on sleepered track to allow sufficient clearance below the firebox. Ade used the large fork lift truck to convey the ashpan to the far end of the shed.
Fitting the heavy ashpan can be an awkward task and no less than Ade, Matt Crabtree, Tim, Sam, Ed and Alan are involved. Needless to say, brute force and plenty of wooden packing won the day.
On Friday, Roger was found lying down on the job as he painted the Furness Railway water crane.
Fred also took advantage of the better weather to add some paint.
John Davis also made the best of the weather to polish the copper top of Fluff‘s chimney.
With much relief, John Dixon successfully removed the formers from FR 20’s brick arch without any unplanned collapse. The engine’s hand rails have had to be fully stripped of any paint to enable them to be fitted through the stanchions, which gave Fred a job on Friday. Even then it was quite a fight to fit the right hand rail, but persistence won through and FR 20 is shown below in its current state.
In the meantime, Alan has been adjusting the smaller dome cover to enable the new larger injector steam valves to the fitted.
The Fluff gang of Paul Newton, John Davis and Phil Bell have refitted the left hand sand box.
It was then the turn of the cab side to be fitted back into place, under the supervision of Mike Rigg.